• Roof repairs & alterations
• Structural repairs and all external walls made sound
• External groundwork & drainage completed

• All old floors dug out
• Radon gas barrier installed on floor
• Modern DPC installed under new concrete screed
• New floor insulated to modern building regulations

• All walls insulated internally
• Internal timber stud work installed

• First fix plumbing & electrics
• Further insulation work to all walls & ceilings
• Appropriate plaster work completed

• New external timber doors & windows
• External paving & finishing completed

• All second fix work completed
• New Bathroom
• New Kitchen

• Fully opening folding sliding doors installed

• Internal joinery undertaken
• New internal doors, skirting boards & architraves
• Decoration completed

• Project Completion